天博tb·综合体育(中国)官方网站

20 days early! CISDI finish roof construction of Dazhou Steel’s three main melting buildings

Date:2023/11/23 Source: CISDI

Construction of three main buildings at Sichuan Dazhou Steel’s steelmaking plant is moving on a pace.

Roofs have been completed and work is now being carried out on the buildings’ steel structures.

A new vanadium-extracting central control building features three layers of framework and will cover a total floor area of around 5,350m2.

A melting central control building will have four layers and cover a 5,488m2 floor area and a melting water pump house is being built with a single-layer framework and a floor area of around 2,067m2

Construction has taken three months so far and the roofing stage has been achieved early - 20 days less than the contractual schedule. This milestone is a strong indicator for the successful schedule of the whole project. 

 

Teams celebrate the successful roof construction of three main framework buildings

 

 

XML 地图